We’re proud to report that the construction of Willow is well underway. To keep up to date on its progress, register your interest to have updates sent straight to your inbox. You can also see our community come to life via our live site cameras.

In progress:

Stage 16

Titles Estimated: Q2 2024

View Details

67%

Planning100%


Planning100%


Civil Construction69%


Site Establishment100%


Bulk Earthworks100%


Drainage Works90%


Sewer Works90%


Water & Gas Reticulation100%


Subgrade Placement Works100%


Electrical & NBN40%


Footpaths/Asphalt/Linemarking0%


Practical Completion0%


Registration Progress0%


Statement of Compliance0%


Lodge Plan of Subdivision0%


Titles0%


Close Details

Stage 16B

Titles Estimated: Q3 2024

View Details

6%

Planning100%


Planning100%


Civil Construction1%


Site Establishment10%


Bulk Earthworks0%


Drainage Works0%


Sewer Works0%


Water & Gas Reticulation0%


Subgrade Placement Works0%


Electrical & NBN0%


Footpaths/Asphalt/Linemarking0%


Practical Completion0%


Registration Progress0%


Statement of Compliance0%


Lodge Plan of Subdivision0%


Titles0%


Close Details

Completed:

Stage 1

Complete: June 2021

Stage 2

Complete: June 2021

Stage 3

Complete: August 2021

Stage 4

Complete: August 2021

Stage 5

Complete: November 2021

Stage 6

Complete: November 2021

Stage 7

Complete: April 2022

Stage 8

Complete: September 2022

Stage 9

Complete: October 2022

Stage 10

Complete: April 2023

Stage 11

Complete: April 2023

Stage 12

Complete: August 2023

Stage 14

Complete: August 2023

Stage 15

Complete: November 2023

Stage 13

Titles estimated: January 2024

* Estimated title dates are provided as an approximate guide only and are subject to change.

The title date estimates provided are based on current information regarding the design, construction, and relevant authority approvals timeframes for the individual stage. Willow uses this information to provide an estimate of the month (or month/quarter ranges) in which titles will be achieved however this is subject to change and is often influenced by factors which are often outside of the projects control such as weather, contractor delays and authority inspections.

Want to hear more?

Register to learn more about Willow Gisborne.